Skip to content

INSTALLATION

About Installation

For O-SCP to function effectively as a secondary containment system, correct installation adapted to site-specific conditions is essential. Placement, ground preparation, elevation differences and fill materials all influence containment capacity, rainwater management and the ability to monitor system performance over time.

This page summarizes the key principles for installation, placement and configuration of O-SCP within its intended areas of use. For detailed work procedures, dimensions and inspection points, the complete assembly instructions should be followed.

1. Select Placement

Position O-SCP where refueling, equipment parking or handling activities will actually take place.

2. Prepare the Base

Excavate and prepare a level base with the correct slope toward the drainage side.

3. Position the System

Place O-SCP into the prepared base and ensure that the partition wall stands perpendicular to the bottom surface.

4. Fill with Permeable Material

Backfill using load-bearing permeable material capable of supporting machinery loads while allowing liquid to move through the fill material.

Positional Principles for Correct Function

Three key conditions the installation must ensure:

Level Base

The base must be level to ensure the water level inside the system functions as intended and that containment occurs evenly across the surface.

Correct Elevation Toward the Drainage Side

The side containing the partition wall must be positioned lower than the remaining sides to allow controlled management of rainwater.

Perpendicular Partition Wall

The partition wall must stand perpendicular to the base to ensure correct passive water-level regulation and proper spill containment capacity.

Fill with Permeable and Load-Bearing Material

O-SCP is filled with permeable stone material capable of supporting the expected loads while allowing water, oil and other liquids to move downward through the fill. The material should not be compacted in a way that prevents liquids from reaching the bottom of the system.

Check Before the Area Is Put into Use

Checklist

• The fill material is permeable

• Entry and exit can take place from the correct side(s)

• The base is level

• The partition wall is straight

• The drainage side is lower

First Rainfall After Installation

After the first significant rainfall following installation, the water level inside O-SCP should be visually checked to ensure that the system has been installed correctly and that the water stabilizes at the intended level (see image). If the installation has been performed incorrectly, there is a risk that the water level may rise above the drainage side, which can affect the containment capacity of the system.

If the first rainfall is limited, the water level may be too low to visually verify system function and level differences. If required, the system can therefore be equipped with an inspection pipe or another simple level-monitoring solution to simplify inspection and follow-up.

Verification of Water Level

If necessary, O-SCP can be equipped with an inspection pipe or another simple level-monitoring solution to allow visual verification of the system’s water level after installation. This may, for example, be requested in sensitive environments or by supervisory authorities as part of inspection and monitoring procedures.

When the Installation Is Complete

Once O-SCP has been installed, refueling, equipment parking, washing and other operations should take place on top of the protected surface. On the next page, we explain how the system is used in practice and which routines should be followed during daily operation.